CJK delivered the redevelopment of an existing Eir telephone exchange in Drogheda, transforming the facility into a modern data centre environment.
Delivered within a live operational telecommunications facility, the project required the careful transition from legacy infrastructure while maintaining continuity of critical services throughout the programme.
Scope of Work
- Full survey and dilapidation reporting of existing infrastructure
- Phased decommissioning of legacy services
- Installation of new mechanical and electrical systems
- Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT)
- Energisation and post-energisation testing
- Integrated Systems Testing (IST) Levels 4 and 5
- Commissioning and operational handover
Project Complexity
- Delivery within a live, operational telecommunications environment
- Maintenance of uninterrupted critical services throughout works
- Phased decommissioning and migration from legacy infrastructure
- Integration of new systems within an existing operational facility
- Careful coordination of installation, testing and commissioning activities
Delivery Outcome
- Successful conversion of a legacy telephone exchange into a modern data centre facility
- Critical telecommunications services maintained throughout project delivery
- Fully commissioned and energised mechanical and electrical infrastructure
- Infrastructure delivered in line with operational and programme requirements